Design Example of Pile Cap for Concentric Loading
A pile cap have to support a 18”X18” column which is subjected to live load=170 kips and dead load=160 kips under service loading. The column is reinforced with longitudinal bars of 12 No. 7 bars. Consider fy=60 Ksi and f’C =3 Ksi. The diameter of pile is 12”. The ultimate pile capacity=70 kip/pile and service load capacity=42 kip/pile as conformed by testing.
Complete pile cap design will be illustrated here; except
superimposed load weight of pile cap also exerts some load on piles. Lets
consider cap weight exerts 3 kips load on each pile.
superimposed load weight of pile cap also exerts some load on piles. Lets
consider cap weight exerts 3 kips load on each pile.
Thus net service load = (42-3) kips/pile
=39 kip/pile
Total unfactored load= (170 + 160) kips
=330 kips
Pile number required, N =330/39
=8.46 or, 9 piles
Factored load = (1.2X160+1.6X170) kips
=464 kips
i.e. Ultimate load on pile cap, Wu = 464 kips
Ultimate load on pile, Pu = 464/9 kips/pile
=51.56 kips/pile <70 kips
(ultimate pile capacity).
(ultimate pile capacity).
Let’s try to check punching shear failure; at first consider
punching shear due to single pile:
punching shear due to single pile:
Assume an effective depth of cap=18”
Thus punching perimeter, bo = π X
(pile diameter + effective depth of cap)
(pile diameter + effective depth of cap)
=πX(12+18)
inches
inches
=90.25”
Now, permissible shear around single pile, Vc=
4√f’c
b0d
4√f’c
b0d
=4X√3000
X90.25X18
X90.25X18
=355910 lb
=356 kips
Here shear force =Nominal reaction of pile=Pn
Now
=51.56/0.75
=68.88 kips <356 kips.
This means no pile will be punched when effective depth,
d=18”
d=18”
Now what can be punched through pile cap? One is pile
itself; another is column or columns supported by pile cap. Should we check
both cases?
itself; another is column or columns supported by pile cap. Should we check
both cases?
It depends on experience of designer, if he or they has/
have not enough experience, should check both. The basis is to have idea about
punching perimeter relative to load. If a column is heavily loaded and he
selects relatively small size of piles (cross-section) with more pile, the
piles can be punched.
have not enough experience, should check both. The basis is to have idea about
punching perimeter relative to load. If a column is heavily loaded and he
selects relatively small size of piles (cross-section) with more pile, the
piles can be punched.
Again if column load is small and relatively greater
cross-section of pile is chosen, pile may not be punched. But calculation for
punching of column through pile foundation must be checked for all situations.
cross-section of pile is chosen, pile may not be punched. But calculation for
punching of column through pile foundation must be checked for all situations.
Let’s calculate perimeter shear around 18”X18” column.
Consider No.6 (20 mm) bars will be used in pile cap. A 3” clearance is assumed
above pile butt, the pile is embedded in cap by 6”.
Consider No.6 (20 mm) bars will be used in pile cap. A 3” clearance is assumed
above pile butt, the pile is embedded in cap by 6”.
Thus total depth becomes=18”+3”+6”+6/8
=27.75”
The practical depth provided=28.0”
i.e., effective depth will becomes =28.0”-3”-6”-6″/8
=18.25”
So, b0 =4 X (18.25+18)
=145”
Now
ϕVc = ϕ4√f’c
b0d
b0d
=0.75X4X√3000
X145X18.25
X145X18.25
=434823 lb
=435 kips
Vu=PuX8
=51.56X8
=412.5 kips < ϕVc=435
kips
kips
Therefore column will also not be punched.
As shown in Figure below, the critical section runs by
a distance d/2 from column face. Only one pile falls in side of this perimeter,
thus remaining (9-1) =8 Nos.piles contribute in calculating Vu. If critical
section passes through a cross-section of pile or piles by any fraction,
this/those piles reactions are also contribute (added) in calculating Vu.
But a partial contribution is considered (Pu divided by fraction
outside the critical section).
a distance d/2 from column face. Only one pile falls in side of this perimeter,
thus remaining (9-1) =8 Nos.piles contribute in calculating Vu. If critical
section passes through a cross-section of pile or piles by any fraction,
this/those piles reactions are also contribute (added) in calculating Vu.
But a partial contribution is considered (Pu divided by fraction
outside the critical section).
Now we calculate beam shear capacity of pile cap. We
know critical section lies at a distance d from face of column (figure below).
know critical section lies at a distance d from face of column (figure below).
The
width of pile cap, B= (Pile c/c distance) X2+(Pile
dia)X1/2X2+(pile
face to cap edge distance)X2
width of pile cap, B= (Pile c/c distance) X2+(Pile
dia)X1/2X2+(pile
face to cap edge distance)X2
=3’X2+6”/12X2+8”/12X2
=8’-4”
=100”
The critical section lies 18.25” from column face. Now
distance between column face to pile face (inside). In one word, clear distance
among them = 3’-9”/2-6”/12
distance between column face to pile face (inside). In one word, clear distance
among them = 3’-9”/2-6”/12
=1.75”
If all piles lie inside of critical section for beam shear,
no shear is considered to produce shear failure in foundation.
no shear is considered to produce shear failure in foundation.
Thus ϕVc= ϕ2√f’cbd
=0.75X2X√3000
X100X18.25
X100X18.25
=150 kips
Vu=3X51.56
=154.7 kips >ϕVc=150
kips
kips
i.e.,Vu>ϕVc
Thus depth of pile should
be increased, let consider d=19”
be increased, let consider d=19”
ϕVc= ϕ2√f’cbd
=0.75X2X√3000
X100X19
X100X19
=156kips >154.7kips (Vu)
This means the effective depth of 19”is enough to avoid
failure due to punching and beam shear. Beam shear is often called flexure
shear.
failure due to punching and beam shear. Beam shear is often called flexure
shear.
Let’s check bending failure. The critical section is
located at the face of column. For each direction there have three piles to
contribute to bending moment.
located at the face of column. For each direction there have three piles to
contribute to bending moment.
Mn=3×51.56x(21”+6”)x1/12
=348.03 kip-ft
In normal beam section design, the following procedure
is followed, if depth is not fixed.
is followed, if depth is not fixed.
β1=0.85
[for concrete of f’c≤ 4000 psi]
[for concrete of f’c≤ 4000 psi]
Equation (1) is used for strength reduction factor=0.9
We need to establish
Mu ≤ ϕ Mn
= 0.9×0.0135x60xbd2(1-0.59×0.0135×60/3)
=0.61x bd2
=0.61x100xd2
=61d2
=61d2
Consider Mu
= ϕ
Mn
= ϕ
Mn
or, 348=61d2
or,d2= 348/61=5.70
or, d= 2.38”
In checking moment capacity above procedure based on pmax
is not valid here as effective depth is governed mainly by shear and required
depth (2.38”) in far below provided depth 19”. Here in most cases, minimum steel
area governs. Lets check required steel area for this moment.
is not valid here as effective depth is governed mainly by shear and required
depth (2.38”) in far below provided depth 19”. Here in most cases, minimum steel
area governs. Lets check required steel area for this moment.
Assume, a=1 in
=4.18 in2
Now to check assumed a:
=0.9835
in
in
Assume a=0.98 in
i.e.
no more iteration is required. Thus required As=4.18 in2
Now check minimum steel area:
=3x√3000x100x19x1/60000
≥200x100x19x1/60000
≥200x100x19x1/60000
=5.20≥6.33 in2
The controlling value of minimum reinforcement is 6.33 in2
which is more than bending requirement of steel, 4.18 in2.
which is more than bending requirement of steel, 4.18 in2.
i.e. required steel area, As =6.33 in2.
Number of bar required= 6.33/0.44
= 14.4
≈15 (as per previous assumption, No.6 bars are considered)
As ACI code do not allow plain concrete (unreinforced) in pile cap, we have to provide minimum steel as calculated above. Structural engineers sometimes also use shrinkage and temperature steel as minimum steel.
These are
As (min) =0.002bh for fy=40 ksi
=0.0018bh for fy=60 ksi
Earlier we have assumed cap exerts 3 kips load on each pile. Now
we have to check whether it satisfies by 19” depth or not.
we have to check whether it satisfies by 19” depth or not.
Total depth provided=19”+3”+6”+6”/8
=28.75
Total weight of pile cap =8.33×8.33×28.75×150/12
=24936.6lbs
=24.93 kips
Now each pile share equal load this is 24.93/9=2.77 kips
This is below our assumed load’ thus 19” depth is satisfactory
in all respect.
in all respect.
If share load (2.77 kips) calculated above is more than assumed
load (3 kips), we have to revise total calculation assuming new cap load to
calculate net service load on pile.
load (3 kips), we have to revise total calculation assuming new cap load to
calculate net service load on pile.
If opposite situation arise, as in this example, the design is safe but to achieve economy we have check rational difference between two values.